Mid Florida Materials started the closer of our first cell in June 2016.  Since the process started, we have completed the closure of 5 cells. We are currently working on the closure of one more cell while at the same time opening two more.  The process for cell closer includes: a final compaction of the material, a layer of fill dirt on top of the material, a liner is placed on top of the dirt, another layer of dirt covers the liner, top soil covers the fill dirt, and then sod is placed.  See the pictures below to follow the process.

Compacting the materials

Covering the material with fill dirt

Installation of liner

Layer of fill covers the liner

Layer of top soil covers the fill dirt

Cover with grass seed and let it grow!